A lot of maintenance shops that struggle with planning aren’t bad at planning. They’re bad at passdown reporting.


A tech finishes a job, or half-finishes it, and goes home without sending a passdown. It seems small, just one missed note.


The supervisor isn’t worried. He’ll get the update tomorrow before the midday meeting. Techs hate paperwork anyway, right?


But the next morning, the planner has a real problem. He has to publish the plan before the techs’ morning standup.


Was yesterday’s work completed? Partly done? Waiting on a part? He can’t tell, so he has two bad options.


He can assign the job again and risk sending a tech to fix something that’s already fixed, or drop it and risk leaving a priority problem open.


Either way, today’s plan is built on a guess. If the guess is wrong, you lose a day of a tech’s time.


And it’s not just one job. If the planner can’t trust the status of yesterday’s work, he can’t trust the priority order of today’s. You can’t determine what needs to be done if you can’t determine what has already been done.


One missing passdown can wreck an entire day of planning.


We like to treat scheduling problems as a planning-office issue. Sometimes they are, but the dynamic isn’t that simple.


Good planning can’t exist without good reporting and accountability, because without them the plan isn’t worth producing.


And good reporting and accountability can’t exist without a good plan, because without a plan there’s no standard to report against.


It’s a chicken-and-the-egg problem. You have to force both into existence at the same time.


This is why planning fails so often.


You can hire a planner, train him, and schedule work on paper... but only feedback will prevent tomorrow's plan from being pure waste.


If you want accountability to work (without which your planner will only produce bad plans), every assigned job must have a status before the shift ends:

→ Done

→ Not done, and why

→ What’s needed to finish


No exceptions, and no “I’ll tell him tomorrow.” If you wait until tomorrow to report it, you’ve already wasted tomorrow.


The schedule you get tomorrow is built from the passdown you send today.


Does your planner start the morning tracking down what happened last night?

180 OPEX helps manufacturers set clear priorities and follow them across shifts.


Need help with a difficult maintenance problem?

Mac Davis provides hands-on industrial maintenance troubleshooting through 180 IMT.